Phase 2: the schedule
What it produced: a phase-by-phase programme with gates (things that must be true before the next phase can start) and a contractor call-up order. The durations are indicative. The engineer's programme replaces them once drawings are firm.
| Phase | Indicative duration | Trigger / gate |
|---|---|---|
| 0. Drawings, planning, soft quotes | (planning wait) | Now |
| 1. Planning wait + tender firm-up | overlaps | Drawings issued "for tender" |
| 2. Enabling and groundworks | ~4-8 weeks | Gate A: planning decision + construction drawings · Gate B: Commencement Notice / certifier |
| 3. Structure to weathertight | ~8-14 weeks | Foundations signed off |
| 4. Envelope and first fix | ~4-8 weeks (overlaps) | Weathertight |
| 5. Second fix and fit-out | ~6-10 weeks | First fix inspected |
| 6. Externals and close-out | ~3-6 weeks (overlaps) | Snag + completion certificates |
Call-up order: groundworker → structure/steel → roofer → glazing → envelope / insulation / first fix (overlapping) → second fix and heat pump commissioning → joinery, kitchen, bathrooms → flooring and decoration → externals → snag and certifier completion.
How we checked it: against the statutory steps (planning, Commencement Notice 14-28 days before start (council FAQ)) and against lead times we heard when soft-quoting.
Use the checklist to track the same stages.