Built with Grok Bot A family with no building experience, building our dream house with Grok Bot AI agents as our project team. Meet the team & see the work → Unofficial, not endorsed or sponsored by xAI.

Our build

A family with no building experience, building our dream house, with Grok Bot AI agents as our project team.

The house is an older detached home on Galway Bay. We're keeping and refreshing the original house and adding a two-storey extension joined to it by a glass link. The design is stone and dark timber, with lots of glass. Instead of hiring a project manager, we work with a team of AI agents: a project manager, a steel and tender estimator, a grants researcher, a sponsorship lead and this site's editor. Every entry has a "What Grok Bot did" box showing their actual work. Read more in Built with Grok Bot (unofficial).

The diary is the story. The guides, checklist and templates are the practical tools that came out of it.

Privacy and money: the diary is anonymised. We don't publish our address, our family's details or our own budget, estimate or tender figures. When numbers appear, they are areas, quantities or clearly labelled per-unit examples.

Entries

  1. The house, and the brief

    An older detached house with a low BER, a big site and a clear idea - keep the original, add a modern two-storey extension.

    Ireland Summer 2026

  2. Stripping it out ourselves

    We did about 80% of the strip-out ourselves. What it saved, what it didn't, and what to check before you swing a hammer in an older house.

    Ireland September 2026

  3. Big decisions - heat pump, solar, and no basement

    Locking the energy strategy early, and dropping the basement from the project.

    Ireland September 2026

  4. Drawings, and the budget wake-up call

    The tender drawings arrived. The extension was much bigger than our early budget assumed, and there was a lot more steel.

    Ireland October 2026

  5. The steel package

    Turning the structural drawings into a 41-member steel schedule, and the seven questions it raised for our engineer.

    Ireland November 2026

  6. Mapping the grants

    Individual grants or a One Stop Shop? What applies to the old house, what doesn't apply to the new extension, and the order of work.

    Ireland November 2026

  7. Tenders are out

    The tender went out with a standard form of contract, retention and PSCS by the contractor. Tenders are due 20 November 2026; we're aiming to start in Q1 2027.

    Ireland November 2026