The steel package
Before steel quotes came in, we wanted to know what we were buying. So we built our own bill of materials from the structural drawings:
- 41 members: universal beams and columns, parallel flange channels and square hollow sections.
- About 5.6 tonnes of fabricated steel (members, plates and a 10% connection allowance), plus about 1.3 tonnes of reinforcement.
- Every line marked as either read from drawing or assumed.
It raised seven questions for the engineer. None of the lengths were dimensioned. One beam had two different sizes on two drawings. Some lintel types weren't defined. One plan sheet looked like a duplicate. We also needed to know the post heights, the finishes and fire protection, and whether there was enough mesh.
- Estimator took off 41 steel members from the structural sheets: section, grade, quantity, length, kg/m, total kg, finish and drawing reference for each.
- It colour-coded every line green (read from drawing) or orange (assumed) and itemised the plates and cleats from the connection details.
- It raised seven queries for the engineer: undimensioned lengths, a duplicated sheet, a beam shown at two different sizes, undefined lintel types, post heights and foundations, finish and fire protection, and mesh quantity.
- It priced the package from published merchant prices and per-tonne ranges so that we could check fabricator quotes (totals not published).
What we learned: a steel schedule you can check yourself turns a quote in "€ per tonne" into something you can actually compare. Full method: Structural steel for an extension.
Next: Mapping the grants
This is our build diary: one real house in Galway. Costs and decisions are ours, not advice or typical prices. See the guides for the general how-to.