Structural steel for an extension: what a steel package is and how to price it
Big glass openings, open-plan kitchens and rooms with no internal walls all have one thing in common: steel. Your engineer's drawings will show beams and columns with codes like "203x133x30 UB". The steel fabricator will quote in euro per tonne. This guide connects the two, so you can check a steel quote yourself before you accept it.
Only a chartered engineer can design structural steel. Nothing here replaces their design or their fabrication-drawing approval. This guide is about understanding and pricing what they've designed.
What a "steel package" includes
A steel package for a domestic extension usually covers:
- Members: the beams, columns, channels and box sections themselves.
- Fittings: plates, cleats, stiffeners, end plates and base plates (the connections).
- Fabrication: cutting, drilling, welding, then painting or galvanising (dipping in zinc for corrosion protection, usually specified for steel near the outside wall).
- Delivery and erection: lifting into place (often with a lorry-mounted crane or small crane), bolting, and propping.
- Sundries: holding-down bolts, chemical anchors, wall ties and packers.
- Sometimes reinforcement (rebar and mesh for foundations and slabs). It's often priced by the groundworker instead, so check who's pricing it.
What it usually doesn't include: the concrete pads the columns sit on (groundworks), temporary works to hold up the existing house while openings are formed (sometimes the builder, sometimes the fabricator, so ask), and fire protection, unless it's specified.
Reading the section codes
| Code | Name | What it looks like / typical use |
|---|---|---|
| UB (e.g. 203x133x30) | Universal Beam | Tall "I" shape. Spans across openings and carries floors |
| UC (e.g. 152x152x37) | Universal Column | Squarer "H" shape. Used for posts, or heavy short beams |
| PFC (e.g. 200x90x30) | Parallel Flange Channel | "C" shape. Often a lintel over an opening or an edge beam, fixed flat against masonry |
| SHS (e.g. 100x100x6) | Square Hollow Section | Box section. Slim posts, e.g. in a glazed link |
| S275 / S355 | Steel grade | Strength. Your engineer specifies it |
The numbers are depth x width x weight. So a 203x133x30 UB is about 203 mm deep, about 133 mm wide, and weighs 30 kg per metre. For SHS, the last number is wall thickness in mm, not weight. The fabricator looks up its weight per metre. The weight per metre is the key to pricing.
Step 1: Turn the schedule into kilograms
For each member: weight per metre × length × quantity = kg. Add up all the members, then add the fittings.
From the engineer's tender drawings for a two-storey extension with a glazed link (lengths scaled from drawings, to be confirmed by the fabricator):
| Ref | Member | Section | Qty × length | kg/m | kg |
|---|---|---|---|---|---|
| S01 | Portal frame columns, rear corners | 152x152x37 UC | 2 × 5.77 m | 37 | 427 |
| S02 | Portal frame rafters | 203x133x30 UB | 2 × 3.97 m | 30 | 238 |
| S04 | Rear ground-floor screen head beam | 203x203x52 UC | 1 × 5.93 m | 52 | 308 |
| S05 | Galvanised lintel over rear screen | 200x90x30 PFC | 1 × 6.11 m | 29.7 | 182 |
…and so on for 41 members, using UB, UC, PFC and SHS sections.
| Totals | |
|---|---|
| Members | 4,731 kg |
| Plates, cleats, stiffeners (itemised from details) | 428 kg |
| Connection allowance (10% of members) | 473 kg |
| Total fabricated steel | 5.63 tonnes |
| Reinforcement (mesh + bar) | 1.33 tonnes |
For comparison, an "average" house extension might have one or two beams. This design has far more steel than usual because of the portal frame, the big openings and the balcony.
Step 2: Price it the way fabricators do
Fabricators usually price per tonne, split into (a) fabricate, finish and deliver and (b) erect, plus lump sums for sundries.
Per-unit rates used to check quotes on the Galway project (late 2026, ex VAT). These are one project's working assumptions, not market norms:
| Item | Low | Mid | High |
|---|---|---|---|
| Fabricate, galvanise, deliver | €4,000/t | €4,750/t | €5,500/t |
| Erect (incl. small crane) | €900/t | €1,200/t | €1,600/t |
| Bolts, anchors, wall ties, sundries | lump sum | lump sum | lump sum |
| Reinforcement fixing labour | €600/t | €800/t | €1,100/t |
Example only: a 5-tonne package at the mid rates is 5 × (€4,750 + €1,200) = €29,750 ex VAT, plus sundries, plus VAT. Steel and the temporary works into the existing house were flagged as the biggest single swing item in the project's estimate. Get at least three fabricator quotes on the same schedule.
Step 3: VAT on steel, and why supply-only can cost more
Revenue treats the supply and installation of construction work as a construction service, generally at the 13.5% reduced rate. That's subject to the two-thirds rule: if the value of the goods is more than two-thirds of the total price, the goods rate can apply to the whole supply. Supply-only building materials are at the 23% standard rate (Revenue: construction services; Revenue: current VAT rates). A steel package is materials-heavy, so ask your fabricator which rate they'll charge, and why. If you're unsure, ask an accountant. The project estimate assumed 13.5% TO CONFIRM: two-thirds rule test for a typical supply-and-erect steel package.
Step 4: The questions to settle before you accept a price
These are generalised from the queries raised on the real project's drawings. Most steel price "extras" come from one of these:
- Lengths. Are members dimensioned, or scaled from drawings? The fabricator should measure on site and produce fabrication drawings for your engineer to approve before cutting.
- Missing items. Are all lintels in the steel pack? Check every opening on the plans against the schedule.
- Conflicts. Does a beam appear with two different sizes on two drawings? Ask the engineer which one is right.
- Undefined items. Are any lintel types (e.g. "LN01") not defined? Are they steel or precast concrete?
- Posts and foundations. How tall are the posts, and do they sit on new pads or existing foundations?
- Finish. Galvanised, primed or painted? Is any fire protection (intumescent paint or boarding) needed?
- Temporary works. Who designs and provides the props and needles while openings are cut in the existing house?
- Connections. Are connections designed by the engineer or "by fabricator"? This affects the price and who carries the design risk.
- Certification. Ask what certification the fabricator holds for structural steelwork (e.g. EN 1090 factory production control and CE marking) TO CONFIRM: requirement for domestic work, with official source.
- Programme. What's the lead time from approved drawings to delivery, and how many days on site?
Step 5: Make the quotes comparable
Send every fabricator the same drawing set and revision, your member schedule (or ask them to produce one), and a pricing form with these lines: fabrication/finish/delivery, erection, sundries, temporary works (in or out), fabrication drawings, reinforcement (in or out), programme. Then compare them in the quote comparison template.
Where steel fits in the build
Steel normally arrives after foundations and pads are cast and before the roof goes on. In an extension, some members go in during demolition of the rear wall while the house is propped. Your engineer or Assigned Certifier will usually want to inspect steel and connections before they are covered up (see Start here and the checklist).