Quote comparison sheet

Put your own estimate and every tender into the same lines. Then normalise: add back anything a tenderer excluded, so you're comparing complete prices. The Excel version adds up the subtotals, VAT, totals and the difference from your estimate for you.

Download Excel (.xlsx) Download CSV

LineYour estimate (EUR ex VAT)Builder ABuilder BBuilder CNotes / exclusions
1 Preliminaries & PSCS (site set-up, welfare, scaffold, skips, insurances)
2 Demolition / strip-out
3 Substructure (foundations, pads, ground floor slab)
4 Frame & upper floors (incl. structural steel)
5 Roofs
6 External walls & cladding
7 Windows & external doors (install, beyond PC sum)
8 Internal walls, doors & joinery
9 Finishes (plaster, drylining, tiling, flooring fit)
10 Mechanical (heating, plumbing, ventilation)
11 Electrical
12 External works & drainage (incl. wastewater)
13 Attendance on PC items
Measured works subtotalsum of elements 1-13
PC: Windows, doors & screenssame allowance for every tenderer
PC: Kitchen & utilitysame allowance for every tenderer
PC: Solar PVsame allowance for every tenderer
PC: Sanitary waresame allowance for every tenderer
PC: Stairssame allowance for every tenderer
PC: Flooring / tiling / carpetssame allowance for every tenderer
PC: Light fittingssame allowance for every tenderer
PC: Other (list)same allowance for every tenderer
PC sums subtotal
Overheads & profit (OH&P)% or lump sum
Subtotal ex VAT
VAT (check rate: revenue.ie)construction services usually reduced rate; see Revenue
TOTAL incl. VAT
Add back: excluded items (normalised)price anything a tenderer excluded
NORMALISED TOTAL incl. VAT
Programme (weeks)
Earliest start date
Retention %
Payment terms
Validity of tender (days)
Qualifications / exclusions
Tax clearance verified (Y/N)
Insurance certs received (Y/N)
References checked (Y/N)
PSCS role accepted (Y/N)

How to use it: keep all figures ex VAT, then apply VAT at the rate(s) that apply to your job (Revenue: VAT on construction services). Make sure every tenderer priced the same PC sums, and write each tenderer's exclusions in the notes column. See the tendering guide.