How to tender a house renovation in Ireland: a step-by-step for non-builders
"Tendering" just means asking several builders to price exactly the same job, on the same documents, by the same date, so you can compare like with like. Done well, it's the single biggest lever a homeowner has on cost and risk. Done badly, you end up with three quotes for three different houses.
This guide follows the tender for a real renovation and two-storey extension in Galway in late 2026, anonymised.
Step 1: Decide your route (main contractor or trade packages)
There are two common ways to buy a building project:
- One main contractor prices and manages everything. You have one contract, one point of responsibility and one programme. You pay for their overheads and profit (often shown as "OH&P"), and they normally take the PSCS health-and-safety role.
- Direct trade packages: you (or a project manager) hire groundworkers, a steel fabricator, a roofer, an electrician and so on separately. This can save the main contractor's margin, but you carry the coordination risk. If more than one contractor works on site, you also have a legal duty to appoint a PSDP and a PSCS in writing (HSA: home owners).
The Galway project first planned 12 direct-to-trade packages: strip-out, groundworks, structure/steel, envelope, roofing, glazing, electrical and PV, plumbing and heat pump, insulation and plaster, joinery, floors and decoration, externals. Glazing, the heat pump and electrical were "soft-quoted" early because of long lead times. The owner later went to a main-contractor tender, with the contractor providing the PSCS. Both routes are valid. Pick the one you can realistically manage.
Step 2: Don't tender until the documents are ready
Builders can only price what they can see. Before asking for firm prices you need:
- Planning permission (or a clear decision that the work is exempt: Citizens Information).
- Drawings marked "for tender": architectural plans, sections and elevations, plus the structural drawings (foundations, steel, roof).
- A specification or construction notes: insulation, windows (U-values), heating, finishes.
- Answers on who is the Assigned Certifier and how building control works for your job. A new home or an extension over 40 m² needs a Commencement Notice with compliance documentation, unless you opt out (SDCC).
Before that point you can still ask for "soft" or budget prices to test the market, as long as everyone knows they aren't binding.
Step 3: Get your own pre-tender estimate
Know roughly what the job should cost before the quotes arrive. Use a quantity surveyor (QS) if you can. At minimum, measure the floor areas from the drawings and use published cost guides (the SCSI publishes rebuilding-cost guidance).
On the Galway project, the independent pre-tender estimate was built the same way a QS would do it. The floor areas were measured from the tender drawings (147.8 m² existing house plus 125.6 m² new extension). The work was then priced in 13 elements, with the PC sums added, then the contractor's overheads and profit, then VAT at 13.5%, and a low/mid/high range given for each line. Professional fees and a contingency were kept outside the building-contract figure, so the all-in budget was always higher than any tender. (The project's own figures are not published here.)
Example only (not this project): 180 m² × an assumed €2,400/m² = €432,000 measured works. Add 12% OH&P (€51,840) to get €483,840 ex VAT. Add 13.5% VAT (€65,318) for about €549,160 incl. VAT. Then add fees and a 10% contingency separately.
Step 4: Build the tender pack
Send every tenderer the same pack. A good pack contains:
- Invitation letter or email with the return date and time, how to submit, and who to ask questions (template).
- Drawings and specification listed by drawing number and revision.
- Form of contract. In Ireland, many domestic jobs use a standard RIAI form of building contract. The Galway project used one with 5% retention.
- Programme: your target start date and any fixed dates.
- Pricing schedule broken into elements, so quotes can be compared line by line. See the elemental list below.
- PC sums and provisional sums. These are fixed allowances for things not yet chosen (a kitchen, say). Everyone prices the same allowance, so they don't distort the comparison.
- Who does what. Health and safety (PSCS), BCAR documentation from the builder, insurances, the airtightness test, and who orders long-lead items.
- Questions you want answered (template).
A simple elemental breakdown (as used on the Galway tender): 1 Preliminaries & PSCS · 2 Demolition/strip-out · 3 Substructure (foundations, slab) · 4 Frame & upper floors (incl. steel) · 5 Roofs · 6 External walls & cladding · 7 Windows/doors install · 8 Internal walls, doors & joinery · 9 Finishes · 10 Mechanical (heating, plumbing, ventilation) · 11 Electrical · 12 External works & drainage · 13 Attendance on PC items.
The Galway pack had 13 PC sums: windows/doors/screens, kitchen and utility, PV panels, wardrobes, stairs, sanitaryware, tiling, timber flooring, carpets, blinds, shelving, light fittings and patio paving. The pre-tender check found that the window and screen allowance looked well below what whole-house triple glazing plus large screens really costs. If an allowance is too low, every tender looks cheaper than the real job, and the difference comes back later as a variation. Check each PC sum against at least one real quote before you tender.
Step 5: Shortlist and invite
Invite 3 to 5 builders who have done similar work recently. Ask for addresses of jobs you can look at and references you can ring. Give a realistic period to price (2–4 weeks is common for a house) and a fixed deadline.
Step 6: Handle questions fairly
When one tenderer asks a question, answer it in writing to all of them, without saying who asked. If you change a drawing, re-issue it to everyone with a new revision letter and, if needed, extend the deadline.
Step 7: Compare tenders line by line
Put every quote into the same table (quote comparison template). For each element, compare it with your estimate and with the other quotes. Then:
- Normalise: add back anything a builder excluded, so you compare complete prices.
- Check the PC sums are the ones you issued, not swapped for lower figures.
- Read the qualifications and exclusions. Common exclusions are rock excavation, asbestos, ESB and water connections, skips, and making good.
- Check the VAT. Most construction services are at the 13.5% reduced rate, subject to the two-thirds rule, while professional fees are at 23% (Revenue: construction services; Revenue: services connected with property). Supply and installation of a heat pump system is at 9% (Revenue).
- Compare programmes. A cheaper builder who takes six months longer can cost you more in rent.
- Look for outliers. One very low element price usually means something was missed, and you'll pay for it later as an "extra".
Step 8: Check the builder before you sign
- Tax clearance: you can verify a contractor's tax clearance online (Revenue).
- Insurance: ask for public liability and employer's liability certificates and check the dates.
- Registration: check whether the builder is on the Construction Industry Register Ireland (CIRI) TO CONFIRM: statutory status in 2026, and that electricians are registered with Safe Electric.
- References: visit at least one finished job and ring two past clients.
Step 9: Agree the contract
Before work starts, agree in writing: the contract sum, the documents it's based on, start and completion dates, the payment stages (usually monthly or by milestone against a certified valuation), retention (often a few percent, held until the defects period ends), how variations are priced and approved, and who submits which building control documents. Then submit the Commencement Notice 14–28 days before start (council FAQ).