Drawings, and the budget wake-up call
In October 2026 the full tender set arrived: 10 architectural sheets and 7 structural sheets. Then we measured them.
- Our early budget assumed an extension of about 85 m².
- The drawings showed 125.6 m² (70.5 m² ground floor, 55.1 m² first floor).
- The structural sheets showed a steel portal frame, many concrete pads, and a new floor slab in the existing house as well as the extension.
An independent elemental estimate was prepared from the drawings, and it came out above our early budget. We aren't publishing our figures, but the method is in How to tender a renovation.
- Estimator measured the full tender set: floor areas from the plan schedules (extension 125.6 m², total 273.4 m²), foundations, steel, slabs, wall, roof and finish areas, M&E and drainage.
- It produced an independent 13-element estimate with low/mid/high rates and a ranked risk list, all before a single builder's price came in.
- It caught that the floor areas didn't match the original brief and that the extension was far bigger than the early 85 m² assumption.
- It tried to read the architect's native CAD file, couldn't, and asked for PDFs (where it fell short).
What we learned:
- Early €/m² budgets are only as good as the m² you put in. Re-run the budget the day measured drawings arrive.
- Check the floor areas on the drawing schedule against your own records. Ours didn't match the original brief.
- Keep fees and contingency outside the building price, or you'll think you have more headroom than you do.
Next: The steel package
This is our build diary: one real house in Galway. Costs and decisions are ours, not advice or typical prices. See the guides for the general how-to.