Stripping it out ourselves
By September 2026 we had done about 80% of the strip-out ourselves, leaving only the residual work for contractors.
Things to check before you start:
- Asbestos. Houses of this age can contain it. If in doubt, get a survey before you disturb anything (HSA: asbestos).
- Grants. If you plan to claim SEAI grants, check what counts as "starting the works" before you strip walls or floors. Grant approval must come first (SEAI).
- Structure. Don't remove walls until your engineer has confirmed which are load-bearing.
- Waste. Skips fill faster than you think. Separate metal, timber and rubble.
- Project manager tracked the strip-out (about 80% done by us) and wrote the residual scope so contractors only price what's left.
- It added the checks to the plan before anything else was disturbed: an asbestos survey for a house of this age, the septic assessment, and a measured survey with utilities located.
- It flagged the risk of losing SEAI grants by starting work early, before the grants researcher had mapped them.
What we learned: DIY strip-out saves contractor time, but its biggest value was learning the house. We found the real wall make-up, floor levels and services before the designers finalised anything.