Big decisions: heat pump, solar, and no basement
Two decisions in September 2026 shaped everything after:
- Energy strategy locked: an air-to-water heat pump plus solar PV. Underfloor heating in the extension, radiators kept in the existing house. This decides the electrics, the plumbing layout, the BER path and which SEAI grants we can apply for.
- Basement excluded. Leaving it out removed a big cost and risk item and simplified the structure and groundworks.
- Project manager logged both decisions and re-scoped all 12 trade packages and the schedule the same day: no basement, heat pump plus PV, underfloor heating in the extension and radiators kept in the existing house.
- It moved the heat pump, electrical/PV and glazing packages to "soft-quote now", because they're long-lead and they drive other packages.
- Estimator re-ran the early budget model without the basement (figures not published).
What we learned: decide the heating system before the engineer finalises the drawings. A heat pump needs a well-insulated house. SEAI requires a heat-loss check for older homes before you can get the heat pump grant (SEAI).
Next: Drawings, and the budget wake-up call
This is our build diary: one real house in Galway. Costs and decisions are ours, not advice or typical prices. See the guides for the general how-to.