How to get every SEAI grant: eligibility, documents, steps, order of work, and individual grants vs the One Stop Shop
SEAI home energy grants can be worth tens of thousands of euro on an older house. They're also easy to lose: start the work before your grant is approved and that grant is gone. This guide covers the whole process in order. Every amount below was checked on seai.ie on 18 November 2026. Grants changed several times in 2026, so check the linked page again on the day you apply.
The golden rule: "You must have grant approval in place before you start the upgrades" (SEAI: individual grants). SEAI is also clear that "grants cannot be backdated" (SEAI: windows and doors).
Step 1: Check the basics (eligibility)
| Requirement | Detail | Source |
|---|---|---|
| Your home has an MPRN | The 11-digit number on your electricity bill | SEAI: heat pump |
| Age of the home | Insulation: built and occupied before 31 Dec 2010. Windows/doors: before 2011. Heat pump: before 2021. One Stop Shop: before 2011 | wall, windows, heat pump, OSS |
| Registered contractor | Every grant-aided measure must be done by an SEAI-registered contractor who is registered for that type of work | SEAI: heat pump |
| Not already grant-aided | The OSS excludes measures that already received SEAI grants or energy credits (EEOS) | SEAI: OSS |
Extensions: for windows, SEAI says you can claim for "the original part of the house or … any extensions built before 1st January 2011. Extensions built after 1st Jan 2011 are not eligible" (SEAI: windows FAQ). So the new part of a renovation-plus-extension won't attract fabric grants. Keep the quotes for the existing house separate from the new extension. Whether a heat pump that heats both old and new parts is affected is TO CONFIRM with SEAI.
Step 2: Know what's on offer (detached house, maximums)
Figures are maximums for a detached house. Semi-detached, terraced homes and apartments get less on several measures (see the OSS tables). A grant can never be more than the cost of the work (SEAI: heat pump).
| Measure | Individual grant | One Stop Shop |
|---|---|---|
| Heat pump system (air-to-water) | up to €10,500 | €10,500 |
| Central heating upgrade for heat pump (radiators/UFH) | up to €2,000 | €2,000 |
| Boiler scrappage (oil, gas, electric storage or solid fuel removed) | €2,000 | €2,000 |
| Heat pump bundle total | up to €14,500 | (same three parts) |
| Heat pump technical assessment (pre-2007 homes) | €200 | n/a (Home Energy Assessment €350) |
| Attic insulation | €2,000 (€2,500 first-time buyers / qualifying welfare) | €2,000 (€2,500 eligible first-time buyers) |
| Rafter insulation | not listed separately | €3,000 |
| Cavity wall | €1,800 (up to €2,300 on qualifying welfare payments) | €1,800 |
| Internal wall (dry-lining) | €4,500 | €4,500 |
| External wall (the "wrap") | €8,000 | €8,000 |
| Windows (complete upgrade) | €4,000 | €4,000 |
| External doors (max 2) | €800 each (€1,600) | €800 each |
| Heating controls only | €700 | €700 |
| Solar PV | up to €1,800 (up to €9,000 with battery for certain DSP payments) | up to €1,800 |
| Battery (5 kWh+) | €600 flat | not listed |
| Solar thermal (hot water) | €1,200 | €1,200 |
| Floor insulation | not listed | €3,500 |
| Mechanical ventilation | not listed | €1,500 |
| Airtightness | not listed | €1,000 |
| Project management | n/a | €2,000 |
| Post-works BER | €50 | included in the service |
Sources: individual grants, heat pump, wall insulation, windows and doors, One Stop Shop grant tables.
If you receive certain welfare payments, also look at the free Warmer Homes Scheme before paying for anything yourself.
Step 3: Choose your route
Individual grants ("Better Energy Homes") — you pick and manage each SEAI-registered contractor. You apply, pay the full bill, then claim the grant afterwards (SEAI).
- ✅ Full control over trades and timing, so it suits a self-builder already running trades.
- ✅ You can do one measure at a time.
- ❌ No floor insulation, ventilation, airtightness or project-management grants (they're not on the individual grants list (SEAI)).
- ❌ You fund the grant amount until it's paid, which takes 4-6 weeks after your paperwork goes in (SEAI).
One Stop Shop (National Home Energy Upgrade Scheme) — a registered company runs the whole upgrade: assessment, grant application, contractors, project management and BER. It deducts the grants up front from your bill (SEAI: OSS).
- ✅ Wider grant list and no need to fund grants yourself.
- ✅ Access to the government-backed Home Energy Upgrade Loan (SEAI: OSS).
- ❌ The home must reach at least BER B after works and either get a heat pump or improve by 100 kWh/m²/yr (SEAI: OSS).
- ❌ The OSS "will assign a contractor" (SEAI: OSS). You may not be able to use your own trades. Ask.
- ❌ SEAI doesn't publish OSS fees. Compare quotes.
Can you mix the two routes on one house (for example heat pump individually and insulation via an OSS)? SEAI's pages don't say clearly TO CONFIRM with SEAI (01 808 2100).
Step 4: Get the order of work right
The order matters because some grants depend on others.
- Get a BER or assessment first. For a heat pump in a home built before 2007 you need a technical assessment (grant €200) unless your valid BER already shows a Heat Loss Indicator (HLI) of 2.3 W/K·m² or less (SEAI: heat pump).
- Fabric before or with the heat pump. A poorly insulated house won't pass the HLI test, and SEAI says "your home must be well insulated to benefit from a heat pump" (SEAI).
- Windows need good walls and attic. To get the windows grant the house must have "good" attic and wall insulation, or an HLI of 2.3 or less after the works. New windows must be U-value 1.4 or better (SEAI: windows).
- Walls are all-or-nothing. All external walls must be insulated ("whole-surface"). If you alter more than 25% of the home's surface area, the house must reach B2 or have a compliant heating system and attic (SEAI: wall insulation).
- External wall insulation may need ESB Networks to alter the service cable. Check before you start (SEAI: wall).
- Post-works BER last, after all measures are complete.
Step 5: Documents to have ready
To apply (individual route) (SEAI: heat pump):
- You must be the owner of the property
- 11-digit MPRN
- Name and ID number of your registered contractor
- Dwelling type, and the year the home was built and occupied
- The measures you're applying for
- For a heat pump: the Technical Assessment or Self-Declaration Form
To claim (SEAI: heat pump):
- Declaration of Works signed by you, your BER assessor and the contractor (for heat pumps, plus the installer's heating design sheet and Eco Design data sheet)
- Request for Payment form
- Post-works BER
- Tax Clearance Certificate if you get more than €10,000 in grants in one calendar year (Revenue: tax clearance)
- Keep the contractor's safety file
Step 6: Apply, do the work, claim (timeline)
- Get quotes from registered contractors.
- Apply online (approval "in minutes") or by post (offer within 5 working days) (SEAI).
- Accept within 30 days, or you'll have to re-apply (SEAI).
- Complete the works, the BER and the paperwork within 8 months of the offer. If you overrun, SEAI will still process forms submitted within 12 months of expiry if you include a note explaining the delay (SEAI).
- Submit the forms. Payment takes 4-6 weeks, and your home may be inspected (SEAI).
For a big renovation, stage the applications. For example, apply for fabric grants when the insulation and window dates are firm, then apply for the heat pump closer to the time, so the 8-month clock doesn't run out mid-build.
Worked example: adding up the maximums
Example only, using SEAI published maximums. Take a 1980s detached house with a BER of E1 and solid-fuel central heating, planned for an air-to-water heat pump, solar PV, new windows, and insulation of the existing walls and attic. Adding up the maximum grants on seai.ie for the existing house only:
- Individual route (heat pump €10,500 + central heating €2,000 + scrappage €2,000 + technical assessment €200 + external wall insulation €8,000 + attic €2,000 + windows €4,000 + 2 doors €1,600 + PV €1,800 + BER €50) = €32,150. With internal instead of external wall insulation (€4,500), it's €28,650.
- One Stop Shop (heat pump bundle €14,500 + external wall insulation €8,000 + attic €2,000 + windows €4,000 + doors €1,600 + floor €3,500 + PV €1,800 + ventilation €1,500 + airtightness €1,000 + assessment €350 + project management €2,000) = €40,250.
These are ceilings, not promises. The real grant depends on eligibility and on actual costs. A new extension attracts no fabric grants (it is built after 2011). On our own project the existing walls were planned for cavity fill plus internal drylining. Whether two wall measures can be claimed in the same application is TO CONFIRM. SEAI's page only covers a "second wall measure" for homes that already received a wall grant (SEAI).
For context, SEAI publishes median OSS project costs and grants by house type (SEAI: median costs).
Common ways people lose grants
- Ordering or starting work (even stripping out walls) before accepting the offer.
- Using a contractor who isn't registered for that measure.
- Insulating only some walls.
- Fitting the heat pump before the house passes the heat-loss test.
- Letting the 8-month offer expire.
- No tax clearance when grants go over €10,000 in a calendar year.